Principles of Measurement & Estimation

Written Assignment

Semester 1, 2025

GENERAL INSTRUCTIONS:

•    This is an individual assignment.

•    This assignment contains THREE questions. Answer all tasks in each question.

•    Total marks for this assignment: 100 marks, total course weightage and contribution of the assessment component: 30%

•    Submission date: Wednesday, 23 May 2025, no later than 11:59 pm

•    Online submission on Stream: COMPULSORY.

•    Late assignments will be penalised as per the course instructions/ Stream site.

•    The cover page needs to include: Student Name or ID, the course number, the course title and the names of the course teaching team

•    Learning outcomes covered: 1,2,3,4

•    Submission instructions:

-     Submission for questions 1 and 2 MUST be in Ms Excel format. No other file types will be accepted.

-     Question 3 can be submitted in Word or Pdf format

-     You MUST submit the AI declaration form as per the instructions on Stream.

The teaching team: An Le, Chinthaka Atapattu

Question 1 - Girth Calculations (25 marks):

Refer to the provided set of drawings, and calculate the following girths. You should use the standard DIM sheet provided and show all the waste calculations.

1.   External girth of the external wall (5 marks)

2.   Centreline girth of the external wall (5 marks)

3.   Centreline girth of the foundation (5 marks)

4.   External girth of the foundation part A and part B (5 marks)

5.   Internal girth of the foundation part A and part B (5 marks)

Question 2 - Approximate Quantities (45 marks):

Using  the  same  drawing  provided  and  the  standard  DIM  sheet,  calculate  the  following approximate quantities. If any dimensions are not shown, you may make sensible assumptions and clearly list out all the assumptions in the Query Sheet provided.

1.   Excavation for trenches (5 marks)

2.   Concrete for foundation part A and part B (5 marks)

3.   Formwork for foundation part A and part B (10 marks)

4.   90 mm thick External wall – (Timber frame + insulation) (10 marks)

5.   External wall finishes – Brick veneer cladding (5 marks)

6.   Floor finishes (carpets and Tiles) (10 marks)

Question 3 - Cost Indices and Cost Databases (30 marks):

Task 3.1 (10 marks)

You are consultant quantity surveyor. You have the cost database of your company’s projects below:

Project 1:

Base project completed in June 2020

Material cost: $700,000, Labour cost: $300,000

Project 2:

Current project completed in 2024

Material cost: $840,000, Labour cost: $390,000

Your manager asked you to:

- Calculate the indices for labour and materials over the period 2020-2024

- Calculate and the composite index of overall cost increase, over the period 2020-2024, considering the weighted contribution of materials (70%) and labour (30%) .

Task 3.2 (10 marks)

Your company have been approached by the Ministry of Education team to prepare a budget estimation for a new school in Auckland. The MoE has provided the historical cost data for similar projects in September 2021 in the table below. The construction of the new school is planned to start in June 2025.

You are asked to complete the table below using the RLB Tender Price Index Calculator: Link.

Gross  Floor  Areas of new school (m2)

Rate  ($/m2)  in September 2021

Adjusted rate in June 2025

Estimated

construction

cost     in    June 2025

Classroom (2,500)

$         2,121

 

 

Auditorium (1,200)

$         3,450

 

 

Laboratories      and technology

workshops (400)

 

 

$         2,700

 

 

Office (200)

$         2,175

 

 

Total   construction cost

 

 

 

Task 3.3 (10 marks)

Write a short essay (300-500 words), discuss why cost indices and cost data are important for managing construction projects. identify and describe factors that influence the effective use of cost indices and cost data in construction projects. Cite any references you might use.