Hello, dear friend, you can consult us at any time if you have any questions, add WeChat: daixieit

AC220 2020/21 BIT

FURTHER MANAGEMENT ACCOUNTING (AC220)

SECTION A: ANSWER ALL QUESTIONS

(Each question is worth 2.5 marks)

1. A colleague has been discussing Activity Based Costing (ABC) and states the following:

(i) ABC effectively treats overheads as variable costs, varying with some activity called a “cost driver”.

(ii) Unlike traditional absorption costing systems, ABC assumes that products incur overheads in proportion to their production volumes.

Which statements are true?

(a) Both the statements

(b) Only statement (i)

(c) Only statement (ii)

(d) Neither of the statements

2. A company sells three products as follows:

P

Q

R

Budget

Sales (units)

1,000

2,000

1,000

Selling price

£60

£36

£20

Unit variable cost

£32

£12

£8

Actual

Sales (units)

900

2,600

700

Selling price

£64

£32

£18

Unit variable cost

£32

£12

£8

What was the sales quantity variance? (a) £3,600

(b) £4,100

(c) £4,400

(d) £8,000

3. In April a company finds that it has incurred an adverse labour efficiency variance.

What might have caused this?

(a) A delay in production while waiting for supplies to arrive

(b) A rise in the labour rate per hour

(c) Using cheaper but lower quality material

(d) A lower selling price for the finished product

4. A company has a standard cost card which includes: 9 litres of Material Q at £8 per litre = £72

The original budget was to make 8,000 units but the company actually made 10,000 units, buying and using 96,000 litres of Q at a total cost of £816,000.

In hindsight, the average market price was more like £8.80 per litre and it was felt this would have been a fair standard.

What is the material price planning variance for material Q? (a) £24,000 A

(b) £28,800 F

(c) £48,000 A

(d) £76,800 A

5. Division A makes items which it supplies to Division B. Its variable costs of production are £15 per item and it has fixed costs of £6 per item, based on full production. There is a perfect market for the item being transferred and the market price is £30.

What should the transfer price be to ensure goal congruence?

(a) £15

(b) £21

(c) £24

(d) £30

6. Which of the following are not normally objectives of a transfer pricing system?

(a) Goal congruent behaviour

(b) Autonomy of divisions

(c) Maximisation of group profits

(d) Maximisation of divisional manager remuneration

7. A company makes and sells 3 products as follows:

X

Y

Z

Contribution margin

20%

40%

25%

Selling price

£200

£170

£120

Budgeted sales

2,000

1,000

3,000

Fixed costs total £595,000 in the period.

Assuming the products are sold in a constant mix, what is the number of product X sold at the break-even point?

(a) 2,500

(b) 5,000

(c) 10,000

(d) 14,875

8. A company is considering a new product. It will have a selling price of £36, variable cost per unit of £24 and fixed costs of £192,000. It is budgeting to make a profit of £48,000.

What is the expected margin of safety on this product (to the nearest 5%)?

(a) 20%

(b) 25%

(c) 30%

(d) 35%

9. A senior manager wishes to encourage her subordinates to have a relatively high involvement with the costs incurred in their areas of responsibility, but not to be tempted to manipulate the accounting information.

What style of evaluating budget information should she aim for?

(a) Budget constrained

(b) Profit conscious

(c) Cost conscious

(d) Non-accounting

10. A company rewards its sales staff each month by giving a reward to the person with the highest number of orders placed by customers in that month. This has been criticised as not fair because:

(i) it does not allow for uncontrollable factors in the economy

(ii) not all orders are the same size

Which of the criticisms might be valid?

(a) Both criticisms

(b) Only criticism (i)

(c) Only criticism (ii)

(d) Neither of the criticisms

11. A company has only 12,000 kg of raw materials for the coming month and two products, P and Q, details of which are as follows:

P

Q

£

£

Selling price

140

160

Raw material (£8 per kg)

24

32

Labour (£20 per hour)

80

100

What is the correct statement of the material constraint (where p = number of P produced and q = number of Q produced)?

(a) 4p + 5q ≤ 12,000 (b) 3p + 4q ≤ 12,000 (c) 4p + 3q ≤ 12,000 (d) 12p + 16q ≤ 12,000

12. When undertaking linear programming using the graphical method, which of the following statements is correct?

(a) A non-zero shadow price means we are not using all of that resource in the optimal solution

(b) The feasible region will always contain the origin

(c) Any point in the feasible region is a possible production plan

(d) The optimal point will never be on one of the axes

13. A short term project requires 14,000 kg of Material S and 11,200 kg of Material T; Material S is used regularly for other work but Material T no longer has any other use. Details are as follows:

Amount in inventory

Original cost

Current price

Resale value

Material S

16,800 kg

£5

£8

£3

Material T

8,400 kg

£12

£10

£4

What is the total relevant cost of material for the project? (a) £62,000

(b)  £156,800 (c)  £173,600 (d) £198,800

14. A ten week project requires 50 hours of skilled labour and 125 hours of unskilled labour.

The skilled labour is paid £40 per hour, regardless of whether they are fully occupied and there are 75 hours of spare capacity over the ten weeks. Unskilled labour is paid £20 per hour and is fully occupied but would work up to 200 hours overtime paid at an hourly rate which is 50% higher than normal; alternatively, additional short term unskilled labour could be recruited at £28 per hour but would need some introductory training at a total cost of £500.

What is the total relevant cost of labour for the project? (a) £3,750

(b) £4,000

(c) £5,750

(d) £6,000

15. A company is assessing a possible project using NPV but it is concerned that it is more risky than its normal business. One of the directors has suggested:

(i) decreasing the discount rate to allow for the extra risk

(ii) using sensitivity analysis to identify the key estimates Which might be valid approaches?

(a) Both approaches

(b) Only approach (i)

(c) Only approach (ii)

(d) Neither of the approaches

16. A company has £4,000 to invest at time 0 in three possible projects: P, Q and R. Each project is infinitely divisible but cannot be undertaken more than once. Details are as follows:

P

Q

R

£

£

£

Investment needed at time 0

1,400

2,000

3,000

Net present value

448

720

1,020

How much should be invested in project R?

(a) £0

(b) £1,000

(c) £1,350

(d) £2,000

(40 marks)


Section B: ANSWER ANY TWO QUESTIONS

1. Fizzy Ltd is a small company which makes energy drinks. It is well known locally for Zippy, which is a very popular drink with the younger generation, and it sells what it produces to local retailers. The production manager is responsible for both the production of the drink and purchasing the ingredients.

The standard set at the start of the year for the production of one litre of Zippy was as follows:

Carbonated water

0.80 litre at £0.125 per litre

0.10

Vegetable extracts

0.15 litre at £2.00 per litre

0.30

Sugar in liquid form

0.20 litre at £0.50 per litre

0.10

Secret ingredient X

0.05 litre at £10.00 per litre

0.50

Total cost

1.00

Some evaporation is expected and built into the standard, as there is some heating of the mixture during the process.

In October, 8,500 litres of Zippy were produced, and the following ingredients were both purchased and used:

Carbonated water

6,500 litres for £800

Vegetable extracts

1,300 litres for £2,500

Sugar in liquid form

1,800 litres for £867.50

Secret ingredient X

450 litres for £5,000

In November, the average market price of the vegetable extracts rose unexpectedly by 15% due to harvest problems and the production manager at Fizzy spent £1,500 to purchase 700 litres for the production of 4,500 litres of Zippy.

Required

(a) Calculate the material price variance and the material usage variance in October for each of the four ingredients.

(8 marks)

(b) Calculate the material mix variance and the material yield variance for October and comment on the results.

(13 marks)

(c) Calculate the material price and usage variances for vegetable extracts in November and split the price variance into planning and operating variances.

(5 marks)

(d) Discuss the factors to be considered in assessing the performance of the production manager in November.

(4 marks)

(Total: 30 marks)

2. Woodland Comfort Products is a small business run by Jim, which produces three different pieces of outdoor furniture for use in the garden; the products are of high quality and are primarily wood with material cushions. Details for next year are as follows: